News

Six days after opening, Duke Energy’s controversial $3.5 billion power plant in Edwardsport broke down, new regulatory filings show. Critics say ratepayers could foot the bill for repairs ...
North Carolina lawmakers this week will begin considering the nomination to the North Carolina Utilities Commission of Donald ...
In three instances since Monday, May 5, a snake came into contact with equipment in a substation, Duke Energy spokesperson ...
A former lead regulator of the commission charged with overseeing Duke Energy joined a law firm that frequently represents ...
Paul Newton, R-Cabarrus, a former president of Duke Energy's North Carolina operations, who helped write the bill and has led ...
If you care about safe water for all, you should be celebrating the North Carolina Department of Environmental Quality’s decision to order Duke Energy to ... Who should pay for it?
Construction While in Progress, or CWIP, allows Duke to pass on construction costs before their plants go live. Does it save ...
Six days after opening, Duke Energy’s controversial $3.5 billion power plant in Edwardsport broke down, new regulatory filings show. Critics say ratepayers could foot the bill for repairs, despite a ...
Steam rises from the cooling tower of Duke Energy’s Harris nuclear plant ... Through Senate Bill 261, the North Carolina Senate is pushing to adopt a policy called Construction While in Progress ...